Canada-Newfoundland and Labrador Offshore Petroleum Board (C-NLOPB) announced on June 30 it had issued a pair of notices of non-compliance regarding a near-miss on the Hebron Platform.
On May 28, maintenance on a knuckle boom crane on the Hebron Platform using a hydraulic pin puller resulted in a near-miss projectile and dropped object when the hydraulic pin puller failed after being exposed to loads beyond rated capacities. No one was injured.
C-NLOPB’s notice of non-compliance to KCA Deutag said:
- The company’s procedure for pulling the pin did not have enough information about how to do the work safely,
- The original equipment manufacturer’s procedure for the work was not made available to employees,
- A job safety analysis failed to reference that exceeding yield load was a hazard to consider,
- The 30-ton and 60-ton hydraulic jacks were exposed to loads beyond their rated capacities and
- The puller rod was exposed to loads in excess of yield three times.
C-NLOPB’s notice of non-compliance to Exxon Mobil said the operator had “failed to take all reasonable measures to ensure the health and safety” of all employees, that it had failed to ensure the relevant information for the operation was communicated to workers, and that it had failed to ensure a copy of all operating manuals and other procedures and documents were readily accessible on-site.
C-NLOPB instructed both companies to conduct an audit by Sept. 30 to determine what contributed to the non-compliance and ensure people are trained appropriately. Exxon Mobil is also to issue an incident bulletin to the local offshore industry.
Recommended Reading
EOG: Utica Oil Can ‘Compete with the Best Plays in America’
2024-05-09 - Oil per lateral foot in the Utica is as good as top Permian wells, EOG Resources told analysts May 3 as the company is taking the play to three-mile laterals and longer.
ShearFRAC, Drill2Frac, Corva Collaborating on Fracs
2024-03-05 - Collaboration aims to standardize decision-making for frac operations.
Well Logging Could Get a Makeover
2024-02-27 - Aramco’s KASHF robot, expected to deploy in 2025, will be able to operate in both vertical and horizontal segments of wellbores.
Crescent Energy: Bigger Uinta Frac Now Making 60% More Boe
2024-05-10 - Crescent Energy also reported companywide growth in D&C speeds, while well costs have declined 10%.
New Permian Math: Vital Energy and 42 Horseshoe Wells
2024-05-10 - Vital Energy anticipates making 42 double-long, horseshoe-shaped wells where straight lines would have made 84 wells. The estimated savings: $140 million.