DT Midstream’s LEAP Phase 2 pipeline expansion project reached an earlier-than-scheduled mechanical completion on Dec. 6, the company announced, meaning the 400 MMcf/d of new capacity on the line should be available on Jan. 1.
The LEAP pipeline is a 155-mile high-pressure lateral line that collects gas in a network from primarily the Louisiana side of the Haynesville Shale and delivers it to facilities on the Louisiana Gulf Coast. The line serves several petrochemical facilities, but the expansion will be available to support LNG export facilities under construction.
The company also completed its LEAP Phase 1 project ahead of schedule, opening it to service in September. The expansion added 300 MMcf/d of capacity on the line, which has been filled almost immediately, according to East Daley Analytics.
Phase 2 raises total LEAP capacity to 1.7 Bcf/d. DTM expects to start Phase 3, adding another 200 MMcf/d in the second half of 2024.
Recommended Reading
Axis Energy Deploys Fully Electric Well Service Rig
2024-03-13 - Axis Energy Services’ EPIC RIG has the ability to run on grid power for reduced emissions and increased fuel flexibility.
Betting on the Future: Chevron Technology Ventures’ Investment Strategy
2024-04-09 - After a quarter century, Chevron Technology Ventures seeks both incremental and breakthrough technologies with its early-stage investment program.