First oil flowed at phase two of Oil and Natural Gas Corp. Ltd.’s (ONGC) deepwater KG-DWN-98/2 Block in the Bay of Bengal on Jan. 7, the Indian operator announced on Jan. 8.
The waxy crude of the M Field—part of Phase 2—required the use of pipe in pipe technology, which had not been previously used offshore India, according to ONGC.
ONGC estimates the 98/2 project in the Krishna Godavari Basin offshore East India will increase the company’s oil production by 11% and gas production by 15%.
Phase 1 began production in March 2020, with gas flowing from the block’s U Field.
ONCG said the final phase of the 98/2 project in 4,265 ft water depth is on track for the remaining oil and gas fields to begin production by mid-2024. In November, McDermott announced winning a contract to transport and install a central processing platform and living quarters for the 98/2 project.
Peak production is expected at 45,000 bbl/d and 10 MMcm/d.
Recommended Reading
CGG to Change Name to Viridien
2024-05-17 - The company’s new ticker symbol will be “VIRI” and listed on Euronext Paris, effective May 21.
Sector’s Appetite for Capital Remains Amid Consolidation Frenzy, Panelists Say
2024-05-17 - There’s still an appetite for capital in the oil and gas sector—companies just need to think creatively to find it, a number of panelists said during SUPER DUG in Fort Worth, Texas.
SilverBow Resets Shareholder Meeting After $2.1B Crescent Deal
2024-05-16 - SilverBow Resources said it will adjourn its May 21 shareholders’ meeting until May 29 following Crescent Energy’s agreement to buy the Eagle Ford operator.
Blue Racer Midstream Prices Senior Notes Offering
2024-05-15 - Net proceeds from the sale of senior notes will be used to pay off debt and other general corporate purposes.
Petrobras CEO Prates to Step Down
2024-05-15 - Brazil’s President Luiz Inácio Lula da Silva has requested that Petrobras CEO Jean Paul Prates resign following a dispute over dividend payments.